The result is an analysis that, when prepared correctly, is simple to calculate and easy to defend. In the following paragraphs the Fixed Perspective Windows Delay Analysis (“Analysis”) method will be presented, which incorporates the strengths of various retrospective methods, while minimizing, if not alleviating the weaknesses. While each methodology may have its appropriate implementation, certain methodologies can be combined to produce a more reliable and accurate result.
Several of the AACE International’s Recommended Practices (29R-03) are commonly labeled as “Time Impact Analysis”. The broad application of the term “Time Impact Analysis” can lead to significant variances in delay calculations. Contractual requirements for time extension requests using the common term, “Time Impact Analysis”, are increasingly appearing throughout the construction industry. Perfecting the Fixed Perspective Windows Delay AnalysisĪbstract – With the variety of Delay Analysis Techniques available to schedule reviewers and analysts, it is difficult to know and implement the most reliable and effective way of demonstrating an accurate impact calculation caused by delay.